I need some assistance with this scenario.
We have an item on contract "A" that is in PO25. We also have multiple facilities.
Contract "A" has many items. However, there are a couple of items that when purchased by one of the facilities (call them "X", that facility gets a lower price than contract price. So another PO25 record was created...contract "B".
So when you look up the item in PO28, it will show both contracts with all facilities participating.
1) What is the hierarchy that Lawson uses to select which PO agreement to use when both are available? And where can that be changed per facility?
I can't remove facility "X" from contract "A" because their are items on it that facility "X" uses.
Hope I explained this clearly.
Thanks