Hello,
I know that the receiving adjustments are done if there is a change is the received quantity of a poline.
Do we need to have receiving adjustments if there is a change in the PO cost for a poline which is received?
thanks,
Srikanth
we have a setup for ERS...
there are scenarios where we need to change the PO cost for a line after it is being received.
at this point do we need any receiving adjstments to be created or can directly update the new costs
in the receivers?