Recently it was requested that we (IT) find an automated method to track and calculate overtime for employees in California who work 4-10 hour days.
We currently have a separate pay plan and use PR132 to calculate the 1.5x OT for > than 8 hours a day, 1.5x OT for > than 40 hours a week, 2.0x OT for > than 12 hours a day and the 7 consecutive day rule of 1.5x regular rates for the first 8 house and 2x for any hours over 8.
Can anyone share how they track a different work schedule in standard Lawson, and/or additional software used to track and calculate this? We've been asked to calculate OT for this alternate work schedule: 1.5x OT for > than 10 hours a day; 2x OT for > 12 hours; working more than a 40 hour work week, working a non-scheduled work day.